Run a tension bar through the links at the end of the mesh.
													
																	Chain link fence installation method statement. 
									
	
		
	
																	Method statement installation of fencing and gate 1 0 objective of procedure this work method statement covers the fencing works for your project name. 
																	Terminal posts should be set 2 higher than the width of the fabric and line posts 2 lower than the fabric width. 
																	This will incude all the work procedures and instruction that are made by the she and kusile specifications scope this method statement will apply to the instalation of the 2 4 high welding mesh sercurity fence as per drawing supplied by eskom kusile. 
																	Chain link fabric or mesh is usually sold in rolls 4 5 or 6 feet high. 
															
													
									
	
		
	
																	Fence and gate will be doing during the kusile project. 
																	This item shall consist of furnishing and erecting fencing and gates in accordance to the specifications and the details shown on the drawings or as directed by the e r. 
																	The bar makes the end of the fence rigid and provides something to attach to the posts. 
																	Mix a fairly heavy solution as too much water weakens concrete and may cause cracking. 
															
													
									
	
		
	
																	Slope it away from the post to help with water runoff. 
																	Chain link fence internal external. 
																	Leave the concrete a few inches below ground level. 
																	Initially the water will sit on top but eventually will work its way to the bottom. 
															
													
									
	
		
	
																	Civil specifications for the project and owner engineer requirements. 
																	This item shall consist of furnishing and erecting fencing and gates in accordance to the specifications and the details shown on the drawings or as directed by the e r. 
																	Make sure the mark you made earlier is at ground level. 
																	Method statement installation of fencing and gate 1 0 objective of procedure this work method statement covers the fencing works for your project name. 
															
													
									
	
		
	
																	The purpose of this method statement is to illustrate how the existing fence and shelters will be removed from site in proper and safe way. 
																	Installation of chain link fence works to comply with schedule of finishes the general architectural. 
																	The scope of this method of statement is to cover the demolishing methodology of the following. 
																	Chain link fabric height 2 depth of post in ground total post height. 
															
													
									
	
		
	
																	1 part cement 2 parts sand and 4 parts gravel. 
																	Set the line post in place against the layout line adjust it for plumb and temporarily support it in place with braces. 
																	Galvanized steel is the strongest mesh. 
																	Set line posts approx. 
															
													
									
	
		
	
																	Add gravel to the bottom of the post hole for drainage. 
																	Set terminal posts as tight to the string as possible without touching the string. 
																	Set the terminal posts in concrete using a concrete mix as follows. 
																	Simply push the post into the cement mix in the center of the hole. 
															
													
									
	
		
	
																	If using fast set concrete pour the dry mix around each post to a few inches below ground level and add water.